Requests |
Created | Requested | Reason | Status | Call History |
8/29/2023 | 8/30/2023 | | Request Taken | View |
7/27/2023 | 7/28/2023 | | Request Taken | View |
7/26/2023 | 7/27/2023 | | Request Taken | View |
7/10/2023 | 7/11/2023 | | Request Taken | View |
|
Inspections |
Inspected | Inspector | Corrections Written | Corrections Completed | Comments |
8/30/2023 | Connelly, Tony | 0 | 0 | |
7/28/2023 | Connelly, Tony | 0 | 0 | |
7/27/2023 | Connelly, Tony | 0 | 0 | |
7/17/2023 | Connelly, Tony | 0 | 0 | |
7/11/2023 | Connelly, Tony | 0 | 0 | |
|
Details |
Inspected | Inspection | Result | Comment |
8/30/2023 | Service,New,Underground,480V,>800A | AC - Approved Complete | 1200A SERVICE |
8/30/2023 | Finals,Commercial | AC - Approved Complete | OK PENDING LABELING OF ALL EQUIPMENT - SERVICE/SUPERCHARGERS/CHARGESTATIONS ETC) |
7/28/2023 | Feeder,New,Underground,480V,401-600A | AC - Approved Complete | (2) 600A FEEDERS TO SUPERCHARGERS |
7/28/2023 | Grounding/Bonding,Service,Other | AC - Approved Complete | ELECTRODE TERMINATION/MBJ IN SERVICE |
7/28/2023 | Service,New,Underground,480V,>800A | AP - Approved Partial | SERVICE NEEDS GFP AND ARC ENERGY REDUCTION TESTING DONE (CANNOT APPROVE SERVICE COMPLETE UNTIL TESTING IS DONE/REPORT IS OBTAINE) |
7/27/2023 | Miscellaneous,Other | AP - Approved Partial | PROGRESS INSPECTION/ VERBAL TO KEN-PERFORMANCE TESTING FOR GFP AND ARC REDUCTION MAINTENANCE SYSTEM REQUIRED |
7/17/2023 | Grounding/Bonding,Service,Other | AC - Approved Complete | GROUND RODS AT SERVICE |
7/11/2023 | Cover,Conduit Only,Underground | AC - Approved Complete | 8 CONDUITS FROM SUPERCHARGER LOCATION TO EV CHARGER PEDESTALS |
|
|